Adelaide, Australia, Nov 18, 2009 - (ABN Newswire) - Beach Petroleum Limited (ASX:BPT)(PINK:BEPTF) drilling report for the week ending 18 November, 2009 are attached. Highlights of the week's activities include:
Beach Petroleum Operated Cooper/Eromanga Exploration
The upper 5.6 metres of the Namur Sandstone at Chiton-1 (PEL 91, Beach 40%) has been perforated and was flow-tested for an 80 minute period at an average rate of 2434 barrels oil and 226 barrels of water per day. Facilities are under construction and the well is expected to commence production by early January.
Egypt - North Shadwan Concession - Gulf of Suez
The NS377-3 field development well (Beach 20%) has been cased and production testing to provide data about fluid and reservoir properties has been initiated. The well is expected to commence full production through Petrobel's Ras Ghara processing facility in the second quarter of 2010. Initial production rates are expected to be in the order of 1500 to 2000 barrels of oil per day.
Arrowie Basin (South Australia) - Paralana-2 Geothermal Exploration Well
Evaluation of the Paralana-2 geothermal deep injector well (Beach, well Operator, earning 21%) has commenced. The evaluation program will include both wireline and logging while drilling (LWD) equipment.
--------------------------------------
Well Participants
--------------------------------------
Paralana-2 BPT* 21.00%
GEL 178 PTR 69.00%
Geothermal Exploration TRU 10.00%
Arrowie Basin, SA
-------------------------------------------------------
Weekly Progress & Summary Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs (CST) 18/11/2009 Upper Cannana
Depth: 4012m (TD) or Bolla Bollana
Operation: Conditioning hole prior
to completing log evaluation
program.
Progress: 0m
--------------------------------------
Well Participants
--------------------------------------
NS 394-3 BPT 20.00%
(Burtocal North) BP* 50.00%
Oil Exploration TOE 30.00%
North Shadwan, Egypt
-------------------------------------------------------
Weekly Progress & Summary Primary Targets
-------------------------------------------------------
Report Time: 0600hrs (local) 17/11/2009 Nubia Sandstone
Depth: 3659m (TD)
Operation: Well has been plugged and abandoned.
Progress: 0m
--------------------------------------
Well Participants
--------------------------------------
NS 377-3 BPT 20.00%
Oil Development BP* 50.00%
North Shadwan TOE 30.00%
Egypt
-------------------------------------------------------
Weekly Progress & Summary Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs (local) 17/11/2009 Kareem Formation
Depth: 2872m (1792m TVDSS) TD
Operation: Completing production testing operations.
Progress: 0m
--------------------------------------
Well Participants
--------------------------------------
Dullingari-40DW1 BPT 20.21%
PPL 12 STO* 66.60%
Gas Development ORG 13.19%
C/E Basin, SA
-------------------------------------------------------
Weekly Progress & Summary Primary Targets
-------------------------------------------------------
Report Time: 0600 hrs (CST) 18/11/2009 Patchawarra Formation
Depth: 2623m (TD)
Operation: Well is cased and suspended as a future Patchawarra
Formation gas producer.
Progress: 158m
(s) Secondary Targets
(*) Operator
BPT Beach Petroleum Ltd
ORG Origin Energy Resources Ltd
BP BP Exploration (Delta)
PTR Petratherm Ltd
TRU TRUenergy Pty Ltd
STO Santos Limited
TOE TriOcean Energy
Hector Gordon Chief Operating Officer TEL: +61-8-8338-2833
Next Article: Windflow Technology gets $1.8m from NZ Windfarms