WestSide Corporation Limited (ASX:WCL) Coal Seam Gas Drilling And Appraisal Continues

Friday November 6, 11:49 AM

Print This Story RSS

Brisbane, Australia, Nov 6, 2009 - (ABN Newswire) - WestSide Corporation Limited (ASX:WCL) continues a multi well program in ATP 688P in the northern Bowen Basin to confirm coal in the P seam and Goonyella seams of the Moranbah Coal Measures in preparation for the drilling of two sets of horizontal chevron-style dual-lateral wells (Tilbrook #L9a and #L9b, Tilbrook #L10a and #L10b) which are planned to intersect with new vertical wells (Tilbrook #9 and #10).

Based on the results of the Tilbrook #9a well it is now planned to drill Tilbrook T9 prior to T10a and T10b to assist in the design of the Tilbrook #L9 lateral set. Tilbrook #9 is planned as a vertical production well.

Latest activity - Tilbrook #9a

The Tilbrook #9a vertical exploration well has been drilled to a depth of 506m, logged, subjected to two drill stem tests and cased. The well shows more than 9 metres of net coal.

Summary : ATP 688P coal seam gas drilling program (Oct - Nov)

--------------------------------------------------
Well          Well Type    Spud Date   Finish Date
--------------------------------------------------
Tilbrook#9a   Exploration  16 Oct 2009  5 Nov 2009
--------------------------------------------------
Well          Current Status
--------------------------------------------------
Tilbrook#9a   Drilled to 506m, logged, cased and 2 DST's
              complete. Suspended as future producer.
==================================================

--------------------------------------------------
Well          Well Type    Spud Date   Finish Date
--------------------------------------------------
Tilbrook#9    Exploration  8 Nov 2009  20 Nov 2009
vertical                   (Planned)    (Planned)
--------------------------------------------------
Well          Current Status
--------------------------------------------------
Tilbrook#9    Preparing to drill then shutdown for
vertical      a planned crew break.
==================================================

--------------------------------------------------
Well          Well Type    Spud Date   Finish Date
--------------------------------------------------
Tilbrook#10b  Exploration  22 Nov 2009 4 Dec 2009
                            (Planned)   (Planned)
--------------------------------------------------
Well          Current Status
--------------------------------------------------
Tilbrook#10b  Site preparation completed.
==================================================

--------------------------------------------------
Well          Well Type    Spud Date   Finish Date
--------------------------------------------------
Tilbrook#10a  Exploration  6 Dec 2009  12 Dec 2009
                            (Planned)    (Planned)
--------------------------------------------------
Well          Current Status
--------------------------------------------------
Tilbrook#10a  Site preparation in progress.
==================================================
Boart Longyear is the drilling contractor.

Expected operations in the next week

Commence drilling T9. Site preparations will continue at Tilbrook #10a.

ATP 688P and ATP769P coal seam gas seismic program (Tilbrook, Mount Saint Martin and Paranui)

WestSide has completed its seismic acquisition program in the Tilbrook and Mount Saint Martin areas of ATP 688P and in Paranui in ATP 769P.

Latest activity

Seismic acquisition over a 10km distance was commenced at Paranui on 3 November and was completed on 4 November.
Summary : Seismic program
-----------------------------------------------------------------
Area           Type         Start     Finish Date  Current Status
-----------------------------------------------------------------
Mt St Martin  5 km of    19 Oct 2009  21 Oct 2009  Completed. 
(ATP 688P)    Vibroseis                            Data processing
Tilbrook      5 km of    22 Oct 2009  23 Oct 2009  Completed. 
(ATP 688P)    Vibroseis                            Data processing
Paranui       10 km of    3 Nov 2009   4 Nov 2009  Acquisition 
(ATP 769P)    dynamite                             completed.
              seismic
=================================================================
Expected operations in the next week

This completes the acquisition of seismic in this program. Data processing and analysis will continue.

About Westside Corporation Limited:

WestSide Corporation Limited is listed on ASX (ASX:WCL) and has interests in coal seam gas (CSG) projects in Queensland and Indonesia. WestSide is currently operating an appraisal program in ATP 769P (Paranui) and ATP 688P (Tilbrook, Mount Saint Martin and Bald Hill) sites in Queensland's Bowen Basin, and is also assessing the CSG potential of certain coal deposits in Indonesia through its relationship with PT Bumi Resources TBK, one of Indonesia's largest coal miners.

Contact:
WestSide Corporation Ltd
Angus Karoll
Chairman and CEO
TEL: +61-7-3020-0900
 


Source:

Westside Corporation Limited

Copyright (C) 2009 ABN Newswire. All rights reserved.

Print This Story RSS

Next Article: Drillsearch Energy Ltd (ASX:DLS) Drilling Resumes At Tintaburra Block Development
Previous article: Exide Technologies Launches ReStore Energy Systems Division to Develop New Renewable Energy Storage and Lithium Ion Energy Systems for High-Growth Glo


Search:
Advertise with us | Privacy Policy | Terms of Service | Help
Copyright © 2009 Yahoo! All rights reserved.
Yahoo!Xtra: A Yahoo!7/Telecom New Zealand Company.